CITICORE SOLAR Pangasinan, Inc. (CSPI), a unit of the Saavedra-led Citicore Renewable Energy Corp. (CREC), is seeking approval from the Energy Regulatory Commission (ERC) to develop connection facilities for its solar farm in Pangasinan.
CSPI has proposed to develop P176.19-million interconnection facilities that will connect its 90-megawatt (MW) Sta. Barbara 1 Solar Power Project to the Luzon grid, according to its filing with the ERC.
The connection will be made through a 69-kilovolt transmission line leading to the Balingueo Substation of the National Grid Corp. of the Philippines (NGCP).